A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?


A.

Retrieve the documentation that shows the resource allocation.


B.

Examine ways of modifying the scope of the project.


C.

Adopt a resource leveling procedure to level the resources.


D.

Perform an impact analysis to see the effect on the project.