PMI Project Management Professional (2025 Version) PMP Question # 418 Topic 42 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 418 Topic 42 Discussion

PMP Exam Topic 42 Question 418 Discussion:
Question #: 418
Topic #: 42

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?


A.

Request the team to work more for on-time delivery.


B.

Request the team to focus on doing better planning.


C.

Request the replacement of certain team members.


D.

Request management for a high-performing team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.