PMI Project Management Professional (2025 Version) PMP Question # 447 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 447 Topic 45 Discussion

PMP Exam Topic 45 Question 447 Discussion:
Question #: 447
Topic #: 45

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?


A.

Keep activities as planned regardless of the resource change.


B.

Update the burndown chart to reflect this resource's absence.


C.

Have a meeting with the resource to understand the issue.


D.

Request an additional resource to finish the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.