Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 447 Topic 45 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 447 Topic 45 Discussion

PMP Exam Topic 45 Question 447 Discussion:
Question #: 447
Topic #: 45

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?


A.

Reduce the priority of project risks as all remaining risks are low-level


B.

Notify stakeholders that all high-level risks have been resolved


C.

Reevaluate identified risks and update the risk register


D.

Reclassify low-level risks as high-level risks


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.