Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 431 Topic 44 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 431 Topic 44 Discussion

PMP Exam Topic 44 Question 431 Discussion:
Question #: 431
Topic #: 44

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?


A.

Update the quality management plan for the overall project


B.

Ask the client to verify and accept the tasks that have been completed


C.

Close out the project tasks that have been completed


D.

Update the communications management plan for the overall project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.