PMI Project Management Professional (2025 Version) PMP Question # 442 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 442 Topic 45 Discussion

PMP Exam Topic 45 Question 442 Discussion:
Question #: 442
Topic #: 45

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?


A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.


B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.


C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.


D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.