PMI Project Management Professional (2025 Version) PMP Question # 441 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 441 Topic 45 Discussion

PMP Exam Topic 45 Question 441 Discussion:
Question #: 441
Topic #: 45

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?


A.

Ask the team leader to assign other resources.


B.

Update the issue log.


C.

Include this in the risk register.


D.

Escalate the issue to the functional manager.