Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 443 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 443 Topic 45 Discussion

PMP Exam Topic 45 Question 443 Discussion:
Question #: 443
Topic #: 45

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?


A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.


B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.


C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.


D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.