PMI Project Management Professional (2025 Version) PMP Question # 443 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 443 Topic 45 Discussion

PMP Exam Topic 45 Question 443 Discussion:
Question #: 443
Topic #: 45

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?


A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.


B.

Create a salience model to determine if the employee will have influence on the project.


C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.


D.

Assess the influence and power of the employee to see if the employee will add value.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.