PMI Project Management Professional (2025 Version) PMP Question # 444 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 444 Topic 45 Discussion

PMP Exam Topic 45 Question 444 Discussion:
Question #: 444
Topic #: 45

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?


A.

Ask the team to focus only on the goal, not on ad hoc meetings.


B.

Coach the project owner about the implications of unplanned meetings.


C.

Discuss the issue with the project owner at the retrospective meeting.


D.

Escalate the situation to management because it is affecting the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.