PMI Project Management Professional (2025 Version) PMP Question # 445 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 445 Topic 45 Discussion

PMP Exam Topic 45 Question 445 Discussion:
Question #: 445
Topic #: 45

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?


A.

Plan for continuous validation of the product.


B.

Discuss adding business scenario tests with the customer.


C.

Discuss adding additional test cases with the product owner.


D.

Add more test scenarios based on the issues found.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.