Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 440 Topic 45 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 440 Topic 45 Discussion

PMP Exam Topic 45 Question 440 Discussion:
Question #: 440
Topic #: 45

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?


A.

The team with the higher velocity is performing better and should be rewarded.


B.

The issue should be addressed as part of a retrospective in the next iteration.


C.

The velocity should not be compared as teams can size items differently.


D.

The velocity of both teams should be compared at the end of every iteration.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.