Question #: 439
Topic #: 44

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?


A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.


B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.


C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.


D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.