PMI Project Management Professional (2025 Version) PMP Question # 438 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 438 Topic 44 Discussion

PMP Exam Topic 44 Question 438 Discussion:
Question #: 438
Topic #: 44

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?


A.

Attend only the program meetings where the market launch is being monitored


B.

Provide an answer via email recommending a division of tasks between both roles.


C.

Politely inform the program manager that attending these meetings is no longer required.


D.

Schedule a meeting to discuss the different perspectives and agree on a decision.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.