Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 438 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 438 Topic 44 Discussion

PMP Exam Topic 44 Question 438 Discussion:
Question #: 438
Topic #: 44

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?


A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments


B.

Incremental delivery and frequent backlog refinement based on user feedback


C.

Iterative development and collection of frequent feedback from project team members


D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.