PMI Project Management Professional (2025 Version) PMP Question # 437 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 437 Topic 44 Discussion

PMP Exam Topic 44 Question 437 Discussion:
Question #: 437
Topic #: 44

One of the team members is always late to the daily standup meeting. What should the project manager do?


A.

Schedule the meeting at the end of the day to accommodate everyone.


B.

Ignore the situation since the team member is accomplishing their deliverables.


C.

Reinforce the ground rules for standup meetings with the entire team.


D.

Speak with the team member directly to reinforce the ground rules.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.