Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 437 Topic 44 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 437 Topic 44 Discussion

PMP Exam Topic 44 Question 437 Discussion:
Question #: 437
Topic #: 44

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?


A.

Stakeholders are satisfied with the current status.


B.

The project is under budget and on schedule


C.

The project is aligned with the project charter


D.

The protect is aligned with the benefits management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.