PMP Exam Topic 42 Question 411 Discussion:
Question #: 411
Topic #: 42

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?


A.

Raise the issues in the retrospective and propose solutions


B.

Inform management that commitments will not be met.


C.

Involve management to help resolve the conflicts


D.

Coach the team both as a whole and individually