PMI Project Management Professional (2025 Version) PMP Question # 413 Topic 42 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 413 Topic 42 Discussion

PMP Exam Topic 42 Question 413 Discussion:
Question #: 413
Topic #: 42

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?


A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.


B.

Add more iterative techniques to improve stakeholder learning.


C.

Identify all the critical stakeholders during the project initiation.


D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.