Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 7 out of 12 pages
Viewing questions 301-350 out of questions
Questions # 301:

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information


B.

Scope statement


C.

Issue log


D.

Risk register


Expert Solution
Questions # 302:

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase


B.

Inform the quality team that they need to ensure that the product is in compliance


C.

Ensure that compliance is explicitly mentioned in the relevant requirements


D.

Meet with the team and remind them of the compliance requirements


Expert Solution
Questions # 303:

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.


B.

Refer to the lessons learned to determine the impact on the external environment.


C.

Recommend postponing the project until the uncertainty is resolved,


D.

Highlight the concern to the project sponsor in the next project review meeting,


Expert Solution
Questions # 304:

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.

Verified applicable budget inputs related to this project


B.

Assigned the same project resources to this project


C.

Estimated a budget for the project's quality management


D.

Determined a budget reserve for this project


Expert Solution
Questions # 305:

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.

Explore the minimum requirements of the product and their feasibility.


B.

Explain the resource constraints of the project to management.


C.

Outsource the management of the product to an external team.


D.

Conduct a detailed risk analysis to highlight the risks in the project.


Expert Solution
Questions # 306:

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.


B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.


C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.


D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.


Expert Solution
Questions # 307:

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

Options:

A.

Strive toward continuous improvement


B.

Work together daily as a team


C.

Only share suggestions at the end of the sprint


D.

Follow the sprint planning


E.

Send communications to the entire team


Expert Solution
Questions # 308:

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.


B.

Ensure that all team members complete the training.


C.

Redesign the training courseware to make it interesting.


D.

Retrain the team members responsible for the breaches.


Expert Solution
Questions # 309:

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned


B.

Meet with the technical lead to review the sprint plan


C.

Meet with the product owner to confirm the minimum viable product (MVP) option


D.

Meet with the project team and reprioritize the backlog


Expert Solution
Questions # 310:

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.


B.

Create a contingency plan in case the project deviates from the initial plan.


C.

Create a schedule management plan to ensure the project meets the delivery date.


D.

Create an assumption log and map assumptions to impediments based on the impact to

the project value.


Expert Solution
Questions # 311:

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Question # 311


Expert Solution
Questions # 312:

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint


B.

Ask the team to address this at the next sprint planning instead of at the retrospective


C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance


D.

Work with the product owner to remove the story from the sprint because the points cannot be splits


Expert Solution
Questions # 313:

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.


B.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.


C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,


D.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.


Expert Solution
Questions # 314:

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.


B.

Set up a meeting with the team member to review the team charter.


C.

Ask another team member to meet with this team member for a discussion.


D.

Send a reminder to the team member about the rule being violated.


Expert Solution
Questions # 315:

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.


B.

Reconcile the team member to the key stakeholder's recommendation.


C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action


D.

Work with both the team member and the key stakeholder to reach a consensus.


Expert Solution
Questions # 316:

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.

Invite the client and product owner to all planning, review, and retrospective meetings.


B.

Accept the escalations and manage them so the working relationship with the client is

not impacted.


C.

Review and clarify roles, responsibilities, and the governance model at the next sprint

review meeting.


D.

Invite the product owner to attend all Scrum meetings and define the governance model

and escalation path.


Expert Solution
Questions # 317:

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability


B.

Determine the appropriate approach


C.

Analyze team member influence


D.

Identify levels of decision-making authority


Expert Solution
Questions # 318:

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget


B.

Engaged with the project sponsor to ensure support for the project manager's decision


C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped


D.

Convinced the functional manager to stop the activities that will run beyond the budget


Expert Solution
Questions # 319:

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.

Share project documentation in a repository with exclusive access.


B.

Schedule weekly knowledge-sharing sessions with key stakeholders.


C.

Send periodic emails to senior management with the latest project updates.


D.

Keep project artifacts up-to-date and accessible to all stakeholders.


Expert Solution
Questions # 320:

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves


B.

Discuss the issue with the steering committee to determine the proper course of action.


C.

Coordinate a video conference with the offending team member to resolve the issue


D.

Reassign the offending team member to a different project


Expert Solution
Questions # 321:

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.


B.

The team productivity is higher; therefore, more value is delivered,


C.

The cost is reduced: therefore, the total value delivered is higher.


D.

The risk is significantly reduced; therefore, more value Is delivered.


Expert Solution
Questions # 322:

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.


B.

Review the communications management plan.


C.

Send the CEO one executive summary per week instead of five reports per week.


D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.


Expert Solution
Questions # 323:

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines


B.

Complying with new regulations


C.

Establishing company processes


D.

Certifying sustainable products


Expert Solution
Questions # 324:

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

Options:

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.


B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.


C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,


D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner


Expert Solution
Questions # 325:

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,


B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.


C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.


D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.


Expert Solution
Questions # 326:

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

Options:

A.

Create a risk probability matrix to address the incompatibility.


B.

identify an alternative component in case of incompatibility.


C.

Use the contingency fund to redesign the interface if it is incompatible,


D.

Require the vendor to redesign the incompatible component to fit the system.


Expert Solution
Questions # 327:

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.


B.

Advise the project team on the importance of team engagement,


C.

Invest in coaching and training for all project team members.


D.

Escalate the issue with the human resource (HR) department to take action,


Expert Solution
Questions # 328:

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

Options:

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped


B.

Review the backlogs from similar projects and understand how change requests were implemented


C.

Ask the product owner to follow the change request process to formalize new requirements


D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team


Expert Solution
Questions # 329:

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.

Confirmed that the communication was understood and solicited feedback from the team


B.

Sent the roles and responsibilities matrix along with the project management plan


C.

Discussed the roles with the managers to help explain them to their team members


D.

Briefed each team member on their roles before sending the project management plan


Expert Solution
Questions # 330:

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.


B.

Suggest using an agile approach since customer and team collaboration is critical for project success.


C.

Work with the project manager to develop a new approach that will bring benefits to the project.


D.

Establish a project management methodology that requires the customer to provide daily updates to the team.


Expert Solution
Questions # 331:

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.


B.

Coach the team to solve the problem independently,


C.

Discuss the issue with the management team and provide a solution,


D.

Speak with the team lead about the issue and provide a solution,


Expert Solution
Questions # 332:

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.

Support the team member by removing the blockers and impediments.


B.

Allocate the blockers and impediments to the product owner to resolve.


C.

Insist that the person who raised the blockers and impediments take ownership.


D.

Add any blockers or impediments to the risk register,


Expert Solution
Questions # 333:

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.


B.

Review the process that resulted in this situation.


C.

Stop work until the design document is completed.


D.

Ask the team to document the design.


Expert Solution
Questions # 334:

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.

Create a change request to extend the project's duration and costs.


B.

Provide feedback to the team using project performance evaluations.


C.

Escalate the impact on the schedule to the project sponsor.


D.

Include buffer time in the schedule to absorb future delays.


Expert Solution
Questions # 335:

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.


B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.


C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.


D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.


Expert Solution
Questions # 336:

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.


B.

Report the concern to the agile project management office (PMO),


C.

Inform the product owner of the concern so that i can be addressed.


D.

Open up to the team to work collaboratively to achieve the outcomes.


Expert Solution
Questions # 337:

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

Options:

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.


B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.


C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.


D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.


Expert Solution
Questions # 338:

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.


B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.


C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,


D.

Check with procurement to see if there is another previously used contractor who can develop the task.


Expert Solution
Questions # 339:

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.


B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.


C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.


D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.


Expert Solution
Questions # 340:

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.


B.

Inform the senior manager that they will need a new project management plan for this feature,


C.

Complete the most current feature and release the resources for the new feature.


D.

Analyze the impact of this change and present the options to the senior manager.


Expert Solution
Questions # 341:

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.


B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.


C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).


D.

Ask the client to initiate a change request to make the director accountable for the

decision.


Expert Solution
Questions # 342:

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan


B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis


C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge


D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project


Expert Solution
Questions # 343:

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure


B.

Work breakdown structure (WBS)


C.

Team charter


D.

Project charter


Expert Solution
Questions # 344:

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities


B.

Conduct serial activities on tasks


C.

Increase the number of standup meetings


D.

Perform tasks in parallel


Expert Solution
Questions # 345:

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.

Postpone the required work on the project until school holidays begin


B.

Advise the school to close (or the duration of the project work


C.

Continue the work as planned and inform the school when the project team arrives on-site


D.

Liaise with the school to include nonworking project hours during school start and finish times


Expert Solution
Questions # 346:

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

Options:

A.

Remove the learn member from the team and hue a more skilled one


B.

Ask the technical lead to provide more training to the team member


C.

Ask the technical lead to discuss performance directly with the team member


D.

Meet with the team member to understand the situation and provide feedback.


Expert Solution
Questions # 347:

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute to

projects.


B.

Assign employees to agile projects so they can quickly adjust to the new approach.


C.

Train all employees in agile approaches.


D.

Shift the way the company views, reviews, and assesses employees.


Expert Solution
Questions # 348:

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned


B.

Time management and stakeholder engagement


C.

Cost management and risk management


D.

Stakeholder engagement and lessons learned


Expert Solution
Questions # 349:

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.


B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.


C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.


D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.


Expert Solution
Questions # 350:

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage


B.

Add more float to the overall project schedule


C.

Request additional contingency from the sponsor.


D.

Organize a root cause analysis (RCA) workshop.


Expert Solution
Viewing page 7 out of 12 pages
Viewing questions 301-350 out of questions