Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 301 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 301 Topic 31 Discussion

PMP Exam Topic 31 Question 301 Discussion:
Question #: 301
Topic #: 31

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?


A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive


B.

Remind the team frequently that the project must be delivered on time and within budget


C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork


D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.