Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 302 Topic 31 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 302 Topic 31 Discussion

PMP Exam Topic 31 Question 302 Discussion:
Question #: 302
Topic #: 31

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?


A.

Tell the client about the chance for the potential delay.


B.

Work with the project team to evaluate the potential delay.


C.

Do not disclose the likelihood of a delay as it is yet to happen.


D.

Ask the project sponsor to inform the client in the next update.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.