Question #: 302
Topic #: 31

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?


A.

Propose to close the project because it no longer fits the business values of the organization.


B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.


C.

Calculate float on the project because it has severely affected the project's major critical path.


D.

Request additional resources from the business unit manager due to the project's complexity.