Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 303 Topic 31 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 303 Topic 31 Discussion

PMP Exam Topic 31 Question 303 Discussion:
Question #: 303
Topic #: 31

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?


A.

Allow the team to reevaluate the tasks and determine how they should be allocated.


B.

Maintain the same task allocation structure to avoid any disruption in the project team.


C.

Move the developer to another team and look for a replacement developer.


D.

Request that all quality assurance tasks be allocated to the new resource.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.