PMI Project Management Professional (2025 Version) PMP Question # 303 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 303 Topic 31 Discussion

PMP Exam Topic 31 Question 303 Discussion:
Question #: 303
Topic #: 31

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?


A.

Ask the product owner to update the stakeholders' contact information at every meeting to address any changes.


B.

Update the stakeholder's information and inform them that they must make the team aware of any changes.


C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.


D.

Check the stakeholder register and ensure that every stakeholder's information is correct and current.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.