Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 303 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 303 Topic 31 Discussion

PMP Exam Topic 31 Question 303 Discussion:
Question #: 303
Topic #: 31

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?


A.

Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.


B.

Organize a meeting to mediate the relationship between the customer and the teammember to ensure no feelings are hurt.


C.

Ask the customer to email all requests directly to you and you will ensure they areactioned by the correct team member.


D.

Explain to the customer that the team member was just trying to help and the changescan be reverted if necessary.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.