A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?


A.

Estimate user story points and forecast a budget for that deliverable


B.

Determine the control accounts and use a top bottom estimate


C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs


D.

Calculate the budget at completion (BAC) based on the completed and planned features