PMI Project Management Professional (2025 Version) PMP Question # 304 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 304 Topic 31 Discussion

PMP Exam Topic 31 Question 304 Discussion:
Question #: 304
Topic #: 31

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?


A.

Risk to delivery


B.

Technical complexity


C.

Business value


D.

Estimation accuracy


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.