PMP Exam Topic 31 Question 309 Discussion:
Question #: 309
Topic #: 31

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?


A.

Work with the team and others in the network to assess and prioritize the obstacles.


B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.


C.

Escalate the obstacles to the project sponsor for assistance with resolution.


D.

Determine a change response to identify and resolve the obstacles to move the projectforward.