Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 309 Topic 31 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 309 Topic 31 Discussion

PMP Exam Topic 31 Question 309 Discussion:
Question #: 309
Topic #: 31

A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.

What should the project manager do?


A.

Place the new team member on a performance improvement program.


B.

Ask another team member to take some of the new team member's work.


C.

Assign easier activities to the new team member.


D.

Allocate time within the iterations to mentor the new team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.