PMI Project Management Professional (2025 Version) PMP Question # 310 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 310 Topic 32 Discussion

PMP Exam Topic 32 Question 310 Discussion:
Question #: 310
Topic #: 32

After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?


A.

Speak with the project sponsor to find out if the stakeholder would agree to a one-on-one review session


B.

Log the stakeholder's comments in the risk register as a high-impact threat to the project's completion


C.

Consider the stakeholder's concerns and review the project charter with the project sponsor.


D.

Note the stakeholder's concerns but disregard them with regard to the project activities.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.