PMI Project Management Professional (2025 Version) PMP Question # 311 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 311 Topic 32 Discussion

PMP Exam Topic 32 Question 311 Discussion:
Question #: 311
Topic #: 32

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?


A.

Ensure team B prioritizes the dependent activity in iteration three.


B.

Include the dependent activity in the current iteration for team B.


C.

Assign the two critical activities to team B in iteration two.


D.

Cancel the current iteration and reschedule it with the dependent activity.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.