Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 312 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 312 Topic 32 Discussion

PMP Exam Topic 32 Question 312 Discussion:
Question #: 312
Topic #: 32

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?


A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk


B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members


C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices


D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.