PMI Project Management Professional (2025 Version) PMP Question # 312 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 312 Topic 32 Discussion

PMP Exam Topic 32 Question 312 Discussion:
Question #: 312
Topic #: 32

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?


A.

Help the team members by organizing regular stress-relieving and team- building sessions.


B.

Request additional resources to continue delivering value while reducing team stress.


C.

Support the team during the planning phase to only commit to what they are able to deliver.


D.

Ask individual team members to plan staggered leave to avoid becoming stressed.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.