PMI Project Management Professional (2025 Version) PMP Question # 313 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 313 Topic 32 Discussion

PMP Exam Topic 32 Question 313 Discussion:
Question #: 313
Topic #: 32

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?


A.

Follow the requirements management process.


B.

Follow the stakeholder engagement process.


C.

Follow the risk management process.


D.

Follow the change management process.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.