Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 314 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 314 Topic 32 Discussion

PMP Exam Topic 32 Question 314 Discussion:
Question #: 314
Topic #: 32

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?


A.

Reprimand the team members who did not fill out the status reports.


B.

Justify the team members' behavior to the project sponsor.


C.

Quickly put together a report that will satisfy the project sponsor.


D.

Discuss the issue with the team members at fault.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.