Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 314 Topic 32 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 314 Topic 32 Discussion

PMP Exam Topic 32 Question 314 Discussion:
Question #: 314
Topic #: 32

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?


A.

Obtained external training in QA for the new team member


B.

Delegated QA tasks to the team lead


C.

Made sure the new team member understood all requirements


D.

Ensured the new team member had access to the quality management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.