PMI Project Management Professional (PMBOK 7th Version) PMP Question # 316 Topic 32 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 316 Topic 32 Discussion

PMP Exam Topic 32 Question 316 Discussion:
Question #: 316
Topic #: 32

A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?


A.

Assign team members to deliverables according to their cultures and languages


B.

Ask the PMO to assign a cultural manager to oversee relations between diverse groups


C.

Perform an analysis to better understand the communication needs and preferences of each group


D.

Establish one language as the main language for communications and one official time zone for the project