Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 315 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 315 Topic 32 Discussion

PMP Exam Topic 32 Question 315 Discussion:
Question #: 315
Topic #: 32

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?


A.

Document and accept this risk and communicate this decision to the project sponsor.


B.

Collect feedback from the farmers and keep the information within the project team.


C.

Deliver the information to the stakeholders with the project management office's (PMO)assistance.


D.

Propose a solution to the stakeholders and communicate it to the local farmers.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.