A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?
A.
Request that the vendor provides a manual with all required knowledge
B.
Implement retrospectives with the vendor to gather the required knowledge
C.
Submit a change request to extend the vendor's contract to provide formal training for the team
D.
Conduct daily knowledge transfer standups to ensure that the team is properly trained
According to the PBA Guide, retrospectives are a technique to review the project performance and identify lessons learned, best practices, and improvement opportunities1. Retrospectives are especially useful in agile projects, where they are conducted at the end of each iteration or sprint2. By implementing retrospectives with the vendor, the project manager can ensure that the project team and the vendor share the same understanding of the project goals, requirements, and deliverables. The project manager can also facilitate knowledge transfer and collaboration between the team and the vendor, and address any issues or risks that may affect the project continuity. References: 1: PBA Guide, page 154 2: PMBOK Guide, page 188
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit