Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 317 Topic 32 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 317 Topic 32 Discussion

PMP Exam Topic 32 Question 317 Discussion:
Question #: 317
Topic #: 32

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?


A.

Escalate this issue to the project sponsor.


B.

Communicate the full details of the project activities to the stakeholder and solicit input.


C.

Analyze this stakeholder’s interest and impact.


D.

Share the summary of the project activities with the stakeholder and conclude the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.