Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 317 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 317 Topic 32 Discussion

PMP Exam Topic 32 Question 317 Discussion:
Question #: 317
Topic #: 32

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?


A.

Request that the vendor provides a manual with all required knowledge


B.

Implement retrospectives with the vendor to gather the required knowledge


C.

Submit a change request to extend the vendor's contract to provide formal training for the team


D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.