PMI Project Management Professional (2025 Version) PMP Question # 317 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 317 Topic 32 Discussion

PMP Exam Topic 32 Question 317 Discussion:
Question #: 317
Topic #: 32

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?


A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.


B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.


C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.


D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.