PMP Exam Topic 32 Question 318 Discussion:
Question #: 318
Topic #: 32

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?


A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.


B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.


C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.


D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.