During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?
A.
Work with the product owner to ensure the product backlog is prioritized
B.
Review the project backlog during the team’s coordination meeting
C.
Encourage team members to prioritize the product backlog
D.
Ensure team members are working according to the project management plan
When team members repeatedly ask what to do first, the work is not being clearly ordered by value and urgency. In agile and hybrid environments, prioritization is primarily the product owner’s responsibility, with the project manager facilitating alignment. Working with the product owner to ensure the product backlog is prioritized (A) provides a consistent, visible ordering of work so the team can pull the next highest-priority items without confusion. This supports flow, reduces wasted time in meetings, and improves delivery of business value. Reviewing the backlog daily in the coordination meeting (B) is inefficient and suggests the backlog is not being managed proactively; daily coordination should focus on progress and impediments, not repeated reprioritization. Encouraging team members to prioritize (C) blurs accountability and can create conflicting decisions; teams sequence tasks within the sprint, but they should not redefine product priorities. Relying on the project management plan (D) is too rigid for day-to-day prioritization of evolving work. A well-prioritized backlog enables autonomy, predictability, and productivity.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit