PMI Project Management Professional (2025 Version) PMP Question # 308 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 308 Topic 31 Discussion

PMP Exam Topic 31 Question 308 Discussion:
Question #: 308
Topic #: 31

A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.

What should the project manager do next?


A.

Discuss the issue with the team member in a one-on-one meeting.


B.

Ask the team member to justify the delay during a team meeting.


C.

Review the human resources (HR) policies for relevant corrective actions.


D.

Escalate the performance issue to the team member's functional manager.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.