Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 325 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 325 Topic 33 Discussion

PMP Exam Topic 33 Question 325 Discussion:
Question #: 325
Topic #: 33

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?


A.

Avoid the conflict as the customer feels comfortable with using processes fromcompany A.


B.

Review the historical information and make the decision based on the return oninvestment (ROI).


C.

Ask the team to use company B's processes since they are more familiar with theseprocesses.


D.

Work with the team to analyze which processes are suitable to use and define them inthe ground rules.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.