PMI Project Management Professional (2025 Version) PMP Question # 328 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 328 Topic 33 Discussion

PMP Exam Topic 33 Question 328 Discussion:
Question #: 328
Topic #: 33

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?


A.

Evaluate the impact of nonrenewal of the license.


B.

Escalate the licensing issue to the product owner.


C.

Add a spike to the backlog for an alternative design.


D.

Raise a change request to secure the renewal.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.