Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 328 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 328 Topic 33 Discussion

PMP Exam Topic 33 Question 328 Discussion:
Question #: 328
Topic #: 33

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?


A.

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.


B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response


C.

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.


D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.