Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 328 Topic 33 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 328 Topic 33 Discussion

PMP Exam Topic 33 Question 328 Discussion:
Question #: 328
Topic #: 33

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?


A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly


B.

Divide the project team into groups to execute as small parallel projects, including the informal sector


C.

Gather requirements and convert them into backlog items to quickly deliver value


D.

Execute the projects simultaneously following the project schedule and the communications management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.