Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 330 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 330 Topic 34 Discussion

PMP Exam Topic 34 Question 330 Discussion:
Question #: 330
Topic #: 34

A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?


A.

Analyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success


B.

Post regular updates to the project teams board and email the stakeholder when they are posted so the stakeholder can review at their convenience


C.

Schedule regular review sessions with the stakeholder and the project team so the stakeholder can understand the status and engage with team members


D.

Continue to send status reports by email and schedule one-on-one sessions with the stakeholder so they are regularly debriefed on the project status


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.