Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 330 Topic 34 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 330 Topic 34 Discussion

PMP Exam Topic 34 Question 330 Discussion:
Question #: 330
Topic #: 34

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?


A.

Inform the product owner of the issue and request that they reprioritize the delayed task.


B.

Suggest the team member get more technical training in the next quarter.


C.

Update the risk register to reflect the possible risk of a schedule delay.


D.

Raise this issue during the daily meeting to determine a possible solution with the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.