PMI Project Management Professional (2025 Version) PMP Question # 330 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 330 Topic 34 Discussion

PMP Exam Topic 34 Question 330 Discussion:
Question #: 330
Topic #: 34

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?


A.

Apply appropriate conflict resolution techniques to solve the issue.


B.

Call a team meeting to have a formal discussion of the issue.


C.

Allow the team to work through it on their own unless help is needed.


D.

Engage in individual conversation with each team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.