Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 332 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 332 Topic 34 Discussion

PMP Exam Topic 34 Question 332 Discussion:
Question #: 332
Topic #: 34

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?


A.

Ensured the project team documented lessons learned about the issue


B.

Ensured the project team applied a long-term solution for the issue


C.

Asked the project team to conduct more testing with users


D.

Discussed the issue with the stakeholders


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.