PMI Project Management Professional (2025 Version) PMP Question # 333 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 333 Topic 34 Discussion

PMP Exam Topic 34 Question 333 Discussion:
Question #: 333
Topic #: 34

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?


A.

Counsel both team members and caution them with a final warning.


B.

Escalate the issue to the human resources (HR) manager before a larger problem develops.


C.

Help cultivate self-awareness between the two team members through emotional intelligence (El).


D.

Relocate the two project team members into different project teams.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.