PMI Project Management Professional (PMBOK 7th Version) PMP Question # 333 Topic 34 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 333 Topic 34 Discussion

PMP Exam Topic 34 Question 333 Discussion:
Question #: 333
Topic #: 34

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?


A.

Register the risk and provide appropriate response options.


B.

Register the risk and prioritize the implementation strategy.


C.

Register the risk and escalate it to the procurement team.


D.

Register the risk and escalate it to the project sponsor.