Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 333 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 333 Topic 34 Discussion

PMP Exam Topic 34 Question 333 Discussion:
Question #: 333
Topic #: 34

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?


A.

Deliver to the receiving manager on time, who can then make a knowledge transfer totheir team.


B.

Inform the project sponsor of the two-week delay and replan activities to minimizedelays.


C.

Request that the receiving manager issue a change request to prolong the project bytwo weeks.


D.

Issue an internal change request to secure the resources for an additional two weeks.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.