Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 331 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 331 Topic 34 Discussion

PMP Exam Topic 34 Question 331 Discussion:
Question #: 331
Topic #: 34

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?


A.

Submit a change request to include the manual.


B.

Add the needed manual and update the risk log.


C.

Review the stakeholder engagement plan.


D.

Review the terms and conditions of the contract.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.