PMI Project Management Professional (2025 Version) PMP Question # 331 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 331 Topic 34 Discussion

PMP Exam Topic 34 Question 331 Discussion:
Question #: 331
Topic #: 34

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?


A.

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.


B.

Include the project stakeholders’ needs while planning the project communications strategy.


C.

Designate a team member to respond to the emails from these stakeholders.


D.

Include the stakeholders’ emails in all of the project status communications.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.