PMP Exam Topic 34 Question 331 Discussion:
Question #: 331
Topic #: 34

A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?


A.

Escalate the issue to the IT department and request they check the software on the stakeholder's computer.


B.

Request human resources (HR) intervene and send the stakeholder to appropriate technical training.


C.

Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.


D.

Request the primary stakeholder be replaced to avoid any more delays and budget issues.