Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 334 Topic 34 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 334 Topic 34 Discussion

PMP Exam Topic 34 Question 334 Discussion:
Question #: 334
Topic #: 34

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)


A.

Review the list of stakeholders that will be affected by starting this business initiative.


B.

Continue with the project the way it was planned and validated by the sponsor.


C.

Describe the outcome of the project and business value to all company stakeholders.


D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.


E.

Modify the project management plan and scope of work to avoid future difficulties.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.