Question #: 334
Topic #: 34

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?


A.

Recognize the stakeholder's skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.


B.

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.


C.

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.


D.

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.