PMI Project Management Professional (2025 Version) PMP Question # 334 Topic 34 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 334 Topic 34 Discussion

PMP Exam Topic 34 Question 334 Discussion:
Question #: 334
Topic #: 34

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?


A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.


B.

Review the terms of reference of the steering committee to include the vendor management head.


C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.


D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.