Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 327 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 327 Topic 33 Discussion

PMP Exam Topic 33 Question 327 Discussion:
Question #: 327
Topic #: 33

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?


A.

Identify how the proposed changes will benefit the project in relation to the businesscase.


B.

Ask for a temporary budget increase to avoid cost overruns.


C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.


D.

Assess the schedule delay and begin implementation to avoid additional lags


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.