PMI Project Management Professional (PMBOK 7th Version) PMP Question # 327 Topic 33 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 327 Topic 33 Discussion

PMP Exam Topic 33 Question 327 Discussion:
Question #: 327
Topic #: 33

A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?


A.

Discuss the risk response strategies with the stakeholders


B.

Add buffers to the schedule to accommodate unforeseen changes


C.

Ensure the risk register includes all identified risks


D.

Develop a communications management plan to share updates with stakeholders