PMI Project Management Professional (2025 Version) PMP Question # 323 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 323 Topic 33 Discussion

PMP Exam Topic 33 Question 323 Discussion:
Question #: 323
Topic #: 33

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?


A.

Negotiate a contract change with the subcontractor.


B.

Meet with the client to discuss the issue with the subcontractor.


C.

Inform the subcontractor that they must send the schedule.


D.

Tell the subcontractor to submit a draft schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.