It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?


A.

Address the required changes in the next release


B.

Review and update the acceptance criteria


C.

Put more emphasis on the definition of done (DoD)


D.

Extend the iterations to complete the items