PMI Project Management Professional (2025 Version) PMP Question # 346 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 346 Topic 35 Discussion

PMP Exam Topic 35 Question 346 Discussion:
Question #: 346
Topic #: 35

The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)


A.

Leverage the project governance system to track and manage the project artifacts.


B.

Create a central repository system to assess the effectiveness of the project artifacts.


C.

Review the execution roadmap and ask the legal team to manage the artifacts.


D.

Ensure the project artifacts are kept up to date and accessible to all stakeholders.


E.

Work with the team to determine the process to manage the project artifacts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.