PMP Exam Topic 35 Question 346 Discussion:
Question #: 346
Topic #: 35

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?


A.

Continue with execution since the project was successful up to this phase


B.

Call for business development to revalidate inputs at the next stage gate


C.

Provide the necessary analysis to enable examination of the business value


D.

Request a delay to the stage gate until business development provides the next update