PMI Project Management Professional (2025 Version) PMP Question # 349 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 349 Topic 35 Discussion

PMP Exam Topic 35 Question 349 Discussion:
Question #: 349
Topic #: 35

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office

(PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?


A.

Engage key stakeholders to complete and deliver lessons learned.


B.

Select the same stakeholders for the next project to avoid doing knowledge transfer.


C.

Present the project achievements and delegate knowledge transfer to the steering committee.


D.

Request the PMO to manage the lessons learned repository.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.