PMI Project Management Professional (2025 Version) PMP Question # 348 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 348 Topic 35 Discussion

PMP Exam Topic 35 Question 348 Discussion:
Question #: 348
Topic #: 35

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?


A.

Use the project budget and procure a new server before raising a change request.


B.

Request that the requirement is funded with the business operational expenses.


C.

Apply contingency reserves to procure a server that fits the requirement.


D.

Raise a change request and obtain approval from the project owner.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.