Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 348 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 348 Topic 35 Discussion

PMP Exam Topic 35 Question 348 Discussion:
Question #: 348
Topic #: 35

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?


A.

Meet with the project team to decide how the remaining budget will be spent.


B.

Keep the extra budget as management reserve until project closeout


C.

Give the team extra time to finish tasks within the original timeline


D.

Follow the project escalation policy and communications management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.