A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?
A.
Schedule a meeting with stakeholders and explain the situation.
B.
Discuss the situation with the sponsor and seek their guidance.
C.
Arrange a time to meet with the team to understand the parameters.
D.
Meet with the team to understand the areas of concern.
When taking over a troubled project, the first priority is to understand what is happening operationally—root causes, current constraints, and immediate risks. Meeting with the team to understand the areas of concern (D) provides direct insight into schedule slippage drivers, the nature and source of late changes, technical or process bottlenecks, and what has and has not worked so far. The team is closest to the work and can identify systemic issues such as unclear requirements, weak change control, poor estimation, or quality rework. Explaining the situation to stakeholders (A) may be needed, but doing it first without facts risks misinformation and loss of credibility. Seeking sponsor guidance (B) can help with authority and escalation, but it should be informed by a clear understanding of issues and options. “Arrange a time to meet with the team” (C) is essentially the same intent but less direct; the immediate action is to meet and diagnose. A fact-based understanding enables a recovery plan, including tighter change control and realistic rebaselining if required.
==========
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit