PMP Exam Topic 36 Question 351 Discussion:
Question #: 351
Topic #: 36

A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?


A.

Add more resources to complete the remaining deliverables early.


B.

Review and analyze the risks associated with compressing the schedule.


C.

Prioritize critical activities and skip noncritical activities.


D.

Perform several activities in parallel to compress the schedule.