A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?
Submit