PMI Project Management Professional (2025 Version) PMP Question # 351 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 351 Topic 36 Discussion

PMP Exam Topic 36 Question 351 Discussion:
Question #: 351
Topic #: 36

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?


A.

Consult the risk response plan.


B.

Assign the tasks to another team member.


C.

Update the resource calendar.


D.

Issue a request to the change control board (CCB).


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.