Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 351 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 351 Topic 36 Discussion

PMP Exam Topic 36 Question 351 Discussion:
Question #: 351
Topic #: 36

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?


A.

Emphasize to the teams the importance of meeting the agreed deadlines


B.

Provide appropriate training to compensate for the mismatch.


C.

Update the project schedule to reflect the delay


D.

Accept the risk of the project missing deadlines due to the mismatch.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.