When a key team member, such as the lead design programmer, leaves in the middle of a project, it’s a risk that could have been foreseen and for which a contingency plan might have been created. The project manager should consult the risk response plan, which will have strategies or actions outlined for such eventualities. This is a proactive approach to manage the situation without disrupting the project’s progress and ensures that the project manager is prepared to handle the loss of critical personnel effectively1.
[: = The importance of having a risk response plan that includes strategies for potential personnel changes is emphasized in PMI’s guidelines for risk management. This approach is supported by resources that describe risk response strategies for mitigation, avoidance, transfer, exploitation, enhancement, sharing, and acceptance, which are essential for ensuring positive project outcomes2. Additionally, the role of the change control board is typically to oversee proposed changes to the project plan, not to manage resource allocation or personnel changes3., , ]
Submit