PMI Project Management Professional (2025 Version) PMP Question # 352 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 352 Topic 36 Discussion

PMP Exam Topic 36 Question 352 Discussion:
Question #: 352
Topic #: 36

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?


A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.


B.

Ask the construction manager to meet with the two team members to resolve the situation.


C.

Provide the construction manager with instructions on how to resolve the situation.


D.

Discuss the team members' concern with the construction manager and seek solutions.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.