Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 354 Topic 36 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 354 Topic 36 Discussion

PMP Exam Topic 36 Question 354 Discussion:
Question #: 354
Topic #: 36

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?


A.

Remove those stakeholders from the project since they may negatively affect project goals


B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed


C.

Schedule a meeting with relevant stakeholders to review the project communications plan


D.

Explain to the stakeholders that they must request project updates from the project sponsor


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.