Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 354 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 354 Topic 36 Discussion

PMP Exam Topic 36 Question 354 Discussion:
Question #: 354
Topic #: 36

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?


A.

Set up a training session for all project team members


B.

Reach out to the functional managers for support


C.

Speak individually with each project team member about making the needed updates


D.

Send an email asking all project team members to complete updates at the end of the day


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.