Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 353 Topic 36 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 353 Topic 36 Discussion

PMP Exam Topic 36 Question 353 Discussion:
Question #: 353
Topic #: 36

A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?


A.

Review alternatives with the product owner and agile team.


B.

Involve stakeholders and ask them to descope some features.


C.

Ask the sponsor for additional resources to hold the schedule.


D.

Increase productivity and modify the schedule as needed.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.