Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 353 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 353 Topic 36 Discussion

PMP Exam Topic 36 Question 353 Discussion:
Question #: 353
Topic #: 36

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?


A.

Organize regular meetings with all of the deployment teams to share issues and solutions


B.

Propose that some of the teams delay deployments in their countries


C.

Ask the project sponsor to appoint new managers for the deployment teams


D.

Ask each deployment team to provide a very detailed schedule and action plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.