Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 356 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 356 Topic 36 Discussion

PMP Exam Topic 36 Question 356 Discussion:
Question #: 356
Topic #: 36

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?


A.

Add the competitor's functionalities to the product backlog to improve the product


B.

Ask the sponsor to add more people to the team


C.

Help the team to find a new approach to launch the product as soon as possible


D.

Ask the team to increase the velocity to launch the product as soon as possible


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.