PMP Exam Topic 36 Question 356 Discussion:
Question #: 356
Topic #: 36

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?


A.

Request the vendor to provide the servers on time as penalties may be applied


B.

Wait until the project deadline is reached in order to use contingency funds


C.

Reach out to the vendor to determine a plan to get the project back on track


D.

Review lessons learned from previous projects and take action accordingly