Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 355 Topic 36 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 355 Topic 36 Discussion

PMP Exam Topic 36 Question 355 Discussion:
Question #: 355
Topic #: 36

A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?


A.

Add a percentage for management reserve


B.

Conduct a retrospective with all involved stakeholders


C.

Initiate a recruitment plan to explore the market situation


D.

Align with relevant stakeholders on the procurement strategy


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.